hembg000
Dubai Municipality completes 36% of the Deira stormwater project
15 Apr 2026Dubai Media Office

Dubai Municipality completes 36% of the Deira stormwater project

A field visit marks 36% completion of the AED 500 million Deira drainage network — 60 kilometres protecting thirteen areas of historic Deira, on track for end-2027.

Dubai Municipality's Deira stormwater project builds a 60-kilometre drainage network — worth AED 500 million — protecting thirteen areas of historic Deira, anchored by a pumping station near Dubai Creek.

During a field visit at the 36%-completion milestone, the Director-General reviewed progress on the works, which are on track for completion by the end of 2027.

Read the original release ↗